skip to content skip to search

Agenda

Thursday, November 03, 2011

9:30 AM start time
Utilities represented: Energy Facilities, Electricity


To view all documents related to the following Agenda items, visit eDockets


DELIBERATION ITEMS
No Items


DECISION ITEMS

1 ET2/TL-11-915 Great River Energy Accepted application as complete; approved alternative permitting process; EFP to name public advisor. 
 

In the Matter of the Route Permit Application for the Enterprise Park to Crooked Lake 115kV Transmission Line Project in Anoka County.

Should the Minnesota Public Utilities Commission accept the application as complete? If accepted, should the Minnesota Public Utilities Commission authorize the Department of Commerce to appoint a public advisor and an advisory task force? (PUC: Kaluzniak; DOC: Comments and Recommendations - Langan)

2

E002, ET2/CN-11-826

Northern States Power Company d/b/a Xcel Energy Approved exemption. 
 

In the Matter of the Application of Northern States Power Company d/b/a Xcel Energy and Great River Energy for a Certificate of Need for the Upgrade of the Southwest Twin Cities (SWTC) Chaska Area 69 kV Transmission Line to 115 kV Capacity.

Should the Commission approve the Exemption Request Petition for filing certain date as required by Minnesota Rules Chapter 7849? (PUC: Briefing Papers - Kaluzniak)

3 E002,325/SA-11-934

Northern States Power Company d/b/a Xcel Energy;
City of Waseca

Approved petition. 
 

Joint Request of Northern States Power Company and the City of Waseca for Approval of Service Territory Compensation and Orderly Transfer Agreement. (PUC: Rebholz; DOC: Comments - La Plante) NOTE: Staff agrees with the comments of the Department of Commerce.

*4

E002/M-11-939;
E002/D-08-1201

Northern States Power Company d/b/a Xcel Energy Approved extension. 
 

In the Matter of Xcel Energy's Request for Extension to Submit its 2011 Review of Nuclear Plant Decommissioning;
In the Matter of Northern States Power Company d/b/a Xcel Energy’s 2009 Nuclear Plant Decommissioning Accrual.

Xcel’s Request for an Extension to File its Nuclear Plant Decommissioning Report. (PUC: Dasinger, Gonzalez; DOC: Letter - O'Connell) Xcel Energy Request for Extension

*5 E015/M-11-274 Minnesota Power Approved petition; Minnesota Power to maintain 2011 rate factor until next RRR filing.
 

In the Matter of Minnesota Power’s Petition for Approval of its Renewable Resource Rider and 2011 Renewable Factor.

Should the Commission Approve Minnesota Power’s Petition for Renewable Resources Rider and 2011 Renewable Factors? (PUC: Briefing Papers - Fittipaldi)

*6

ET3/RP-11-918

Dairyland Power Cooperative Accepted plan as complete.
 

In the Matter of Dairyland Power Cooperative’s Integrated Resource Plan for 2011-2026.

Should the Commission make a determination as to the completeness of Dairyland’s Integrated Resource Plan and/or require supplemental info? (PUC: Briefing Papers - Rebholz)

*7

E015/AA-10-933

Minnesota Power Withdrawal granted. 
 

In the Matter of Minnesota Power’s Request for Authorization to Institute an Annual FCA True-up Mechanism in Compliance with the Stipulation and Agreement in Docket No. E-015/GR-08-415

Should the Commission allow the Company to withdraw its request for an annual FCA True-up mechanism?
What action should the Commission take to resolve the disputed issues? (PUC: Briefing Papers - Dasinger)

  * One star indicates agenda item is unusual but is not disputed.
** Two stars indicate a disputed item or significant legal or procedural issue to be resolved.
(Ex Parte Rules apply)